HYTHE by Botanica reaches 52.64% overall progress
The developer's update as of 31 Oct 2026 shows the structure of all four buildings (A–D) at 98.7%, architecture works at 47%, MEP at 26% and landscaping at 63%. The project page lists 30 Apr 2027 as the expected completion date.